A mould trial is a process, not a single event. It starts with a tooling check (T0), moves to first real samples (T1), then to corrected samples and approval (T2). Each stage has its own checks, customer decisions and documents. Treating the trial as one event is how moulds ship with unresolved problems that surface only in mass production.

Why a mould trial is a process, not a single event

The purpose of a trial is to prove the mould and the part before the tool leaves the workshop. That means proving the tool assembles and moves correctly, that the part fills and ejects, that dimensions are inside tolerance, and that the surface meets the agreed standard.

No single shot list can prove all of that at once. A staged trial separates the toolmaking checks from the process checks and from the customer’s approval. Each stage produces information that the next stage needs.

T0: tooling assembly and dry run checks

T0 is the tooling check. The mould is assembled, the mechanisms are cycled, the cooling circuits are pressure-tested and the ejector system is checked. In many projects T0 runs without a full production shot, or with a short run to confirm basic function.

The output is a list of mechanical issues and their corrections: a slider that binds, a cooling line that leaks, an ejector plate that does not return cleanly. Fixing these before a full trial keeps the T1 trial focused on the part rather than on the tool’s basic function.

T1: first shots, dimensions and appearance

T1 is the first real trial. The mould runs in a machine, a process window is established, and the first samples are produced. The samples are inspected for fill, sink, warpage, flash, weld lines, gate appearance and ejection marks, and key dimensions are measured against the drawing.

T1 is also where the process is proven. Shot size, injection speed, holding pressure, cooling time and melt temperature are recorded so the tool can be run again reproducibly. A trial that produces good samples but no process record is only half a trial. Our mould tooling capability page shows the machining and inspection equipment behind this stage.

What a mould trial report should contain

A trial report is the buyer’s evidence. It should include the machine and process settings, material grade and batch, mould actions performed, dimensions measured against the drawing, appearance findings with photographs, and a numbered list of issues with owners and planned corrections.

It should also state clearly what the samples are for: internal correction, customer dimensional approval, or appearance approval. A report that mixes these purposes lets a sample be treated as approved when it was only a first attempt. The mould quality control process explains how inspection records fit into the wider quality system.

T2 and corrections: steel-safe changes first

After T1, corrections are ranked. Steel-safe changes are those that can be made without changing the cavity geometry: polishing a mark, adjusting a lifter, changing a gate insert, adjusting cooling, adding a vent. These are done first because they are low risk and often solve the problem.

Geometry changes are different. Moving a wall, changing a rib or altering a boss means cutting steel, which costs money and time and must be agreed before it happens. The T2 trial then proves that the corrections worked and produces samples for final approval.

Sample approval: who signs off and against what

Sample approval needs a standard. That standard is the drawing plus the agreed cosmetic and functional requirements, not the opinion of whoever happens to open the box. A clear approval record names the sample stage, the dimensions checked, the appearance reference and the person who signed.

Where a buyer has a quality team, the approval often runs through their own PPAP or first-article process. The mould trial report should be written so it can feed that process directly, with measured values and photographs rather than general statements.

Trial at your plant or ours: options for overseas buyers

Most trials run in the mould maker’s plant, using a machine large enough for the tool. For overseas buyers, the practical options are to attend, to join by video, or to receive a recorded trial with measured samples shipped by courier.

Each option needs preparation. Attending needs travel and a schedule. A video trial needs a clear camera view of the mould and the parts. Sample shipment needs packing that protects the parts and a report that arrives with them. The choice should be made before the trial, not after. Our about page describes the Taizhou base where these trials run.

Documents you should receive before shipment

Before a mould ships, the buyer should hold a trial report, dimensional data, an approved sample record, a mould drawing set, a spare-parts list and any maintenance instructions agreed in the contract. These documents are what make the tool usable, maintainable and movable.

A supplier who provides samples but no documents is handing over a working object without its manual. Our mould service covers how documentation, on-site support and after-sales service are handled after the trial.

Frequently asked questions

What is the difference between T0, T1 and T2 samples?

T0 is the tooling check stage, usually without a full production shot. T1 is the first real trial with first samples, used to prove the mould and the part. T2 follows corrections and produces samples for final dimensional and appearance approval. The names are used differently across suppliers, so agree the definitions in writing before the trial.

What should a mould trial report include?

A trial report should list the machine and process settings, material batch, mould actions, dimensions measured against the drawing, appearance findings with photos, and a clear list of issues with owners. It should also state whether the samples are for customer approval or only for internal correction.

Who pays for trial material and sample shipping?

This is a commercial term, not a technical one. Trial material and sample courier costs are sometimes included in the tool price and sometimes charged separately. Agree it in the quotation so the trial is not delayed by a cost discussion after the samples are ready.

Can we attend the mould trial?

Buyers often attend the T1 trial or join by video. Attending lets you see the mould running, discuss appearance and agree corrections on the spot. For overseas buyers who cannot travel, a recorded trial with a written report and measured samples is the practical alternative.

What happens if T1 samples fail the dimensional report?

The trial report should separate steel-safe corrections from changes that require re-cutting. Steel-safe work such as adjusting a lifter, polishing a mark or changing a gate insert is done first. Anything that moves the cavity geometry is quoted and agreed before machining, so the buyer knows the cost and the effect on the tool.

Book a trial and review the report first

Send your part file, mould specification and target trial window to [export@sinomould.com](mailto:export@sinomould.com), or contact SinoMould to arrange a trial and receive a sample report before you commit. With 20+ years of mould making, nearly 40,000 moulds delivered and ISO-certified quality management, SinoMould runs trials as a documented approval process, with the sample report and mould records handed over to the buyer.

Trial stages, documents and approval steps vary by project. Agree the exact sequence and deliverables with your supplier before the tool is built.